Close

District Jail, Kolasib

District Jail, Kolasib : Established and commissioned on 27.11.1990 It is located at 3 kms distance from D.C Court. It has a capacity of accommodating 114 prisoners (98 male and 16 female). All Jail employees headed by Jail Superintendent look after this jail. 90% of them are provided with staff quarters in the jail complex. Indoor and Outdoor items are available inside the Jail.

 

 

 

Re-Construction of District Jail Kolasib

1 Name of Work Re-Construction of District Jail, Kolasib
2 Implementing Agency Mizoram PWD
3 Sanctioning Authority/Fund Source SASCI 2024-2025
Name of Contractor Fredy Vanlalngila, Dinthar, Aizawl
5 Agreement N0. & Date

Agreement Amount

42/CE-BD/2024-2025, Dt. 9.5.2025

₹ 6,47,64,442.00

6 Work Order No. & Date

Agreement Amount

B.20011/84/CE-BD/PWD/2025/35, Dt. 8.4.2025

₹ 6,47,64,442.00

7 Date of Start Dt. 27.5.2025
8 Target Date of Completion Dt. 27.5.2026

 

STATUS OF WORK PROGRESS IN JAILS AS ON 09.07.2026

1. Construction of Male Ward: Estimate : Rs.12614200 (with Go-down and Kitchen) ::All structure is 90% complete. The remaining work is planned to be done in 1 week, starting from now. Ground floor brick work is done with all the windows & doors placed in its position. Plastering process is undergoing as of now.

Kolasib District Jail 1
2. Construction of Go-down and Kitchen: Estimate : included as above)
All structure work is completed, brick work process is ongoing, dyna roof structure is finished, all that’s left is the placement of dyna roof finishing and plastering.
Kolasib District Jail 2

3. Construction of Staff Quarters Type – II  (2 Units):  Estimate :Rs.10697300   All work is finished.
Placing of water storage tank (Syntex) and paint job is finish

Kolasib District Jail 3

4. Construction of Security Main Wall : Estimate :Rs.4743200
The work is finished . Paint work is finished.

Kolasib District Jail 4
5. Construction of Separation Wall 1 : Estimate :Rs.4743200
The work is finished . Paint job is finished.
Kolasib District Jail 5
6. Construction of Security 4 Duty Post: Estimate :Rs.3859200
All Structure work is finished.  Steel work for step is finish. Brick works and plastering process is on going.
Kolasib District Jail 6
7. Construction of Female Ward: Estimate :Rs.10212400
Roof slab process is on going , and the remaining work left will be only the mumty work. Ground floor brick work is 70% complete with all the windows and doors placed in its position.
Kolasib District Jail 7
8. Construction of MRHG Barrack, Kitchen cum Dining Hall: Estimate :Rs.5314300
All work is finished.
Placing of water storage tank(syntax) and paint job is also finished
Kolasib District Jail 8
9. Construction of Visitors Toilet: Estimate : Rs.917600
All work is finished.
Kolasib District Jail 9