District Jail, Kolasib
District Jail, Kolasib : Established and commissioned on 27.11.1990 It is located at 3 kms distance from D.C Court. It has a capacity of accommodating 114 prisoners (98 male and 16 female). All Jail employees headed by Jail Superintendent look after this jail. 90% of them are provided with staff quarters in the jail complex. Indoor and Outdoor items are available inside the Jail.
Re-Construction of District Jail Kolasib
| 1 | Name of Work | Re-Construction of District Jail, Kolasib |
| 2 | Implementing Agency | Mizoram PWD |
| 3 | Sanctioning Authority/Fund Source | SASCI 2024-2025 |
| 4 | Name of Contractor | Fredy Vanlalngila, Dinthar, Aizawl |
| 5 | Agreement N0. & Date
Agreement Amount |
42/CE-BD/2024-2025, Dt. 9.5.2025
₹ 6,47,64,442.00 |
| 6 | Work Order No. & Date
Agreement Amount |
B.20011/84/CE-BD/PWD/2025/35, Dt. 8.4.2025
₹ 6,47,64,442.00 |
| 7 | Date of Start | Dt. 27.5.2025 |
| 8 | Target Date of Completion | Dt. 27.5.2026 |
STATUS OF WORK PROGRESS IN JAILS AS ON 09.07.2026
|
1. Construction of Male Ward: Estimate : Rs.12614200 (with Go-down and Kitchen) ::All structure is 90% complete. The remaining work is planned to be done in 1 week, starting from now. Ground floor brick work is done with all the windows & doors placed in its position. Plastering process is undergoing as of now. |
![]() |
| 2. Construction of Go-down and Kitchen: Estimate : included as above) All structure work is completed, brick work process is ongoing, dyna roof structure is finished, all that’s left is the placement of dyna roof finishing and plastering. |
![]() |
|
3. Construction of Staff Quarters Type – II (2 Units): Estimate :Rs.10697300 All work is finished. |
![]() |
|
4. Construction of Security Main Wall : Estimate :Rs.4743200 |
![]() |
| 5. Construction of Separation Wall 1 : Estimate :Rs.4743200 The work is finished . Paint job is finished. |
![]() |
| 6. Construction of Security 4 Duty Post: Estimate :Rs.3859200 All Structure work is finished. Steel work for step is finish. Brick works and plastering process is on going. |
![]() |
| 7. Construction of Female Ward: Estimate :Rs.10212400 Roof slab process is on going , and the remaining work left will be only the mumty work. Ground floor brick work is 70% complete with all the windows and doors placed in its position. |
![]() |
| 8. Construction of MRHG Barrack, Kitchen cum Dining Hall: Estimate :Rs.5314300 All work is finished. Placing of water storage tank(syntax) and paint job is also finished |
![]() |
| 9. Construction of Visitors Toilet: Estimate : Rs.917600 All work is finished. |
![]() |